Project stages and dates
Phase 1 – Seals Craig to Hawes Car Park
6 October 2025 for approximately 8 to 10 weeks
-
Re-surfacing and pavement widening
-
Minimal traffic management in place with no reduction in parking during works
Work will then pause for the busy Christmas period.
Phase 2 - main High Street works
Starts January 2026 for approximately 12 months, working along the High Street in phases.
We are in the process of appointing a contractor and will be able to provide more detail on construction dates following that.
There will be an opportunity to meet the contractor to hear about the detailed work programme.
Phase 2a
Phase 2b