Queensferry High Street improvements

Project stages and dates

Phase 1 – Seals Craig to Hawes Car Park

6 October 2025 for approximately 8 to 10 weeks

  • Re-surfacing and pavement widening

  • Minimal traffic management in place with no reduction in parking during works

Work will then pause for the busy Christmas period.

Map with grey shading to show work area for road and pavement construction. Text says Seals Craig to Hawes car park October 2025 to December 2025.

Phase 2 -  main High Street works

Starts January 2026 for approximately 12 months, working along the High Street in phases.

We are in the process of appointing a contractor and will be able to provide more detail on construction dates following that. 

There will be an opportunity to meet the contractor to hear about the detailed work programme.

Phase 2a

Map with shading showing area of construction work on Queensferry High Street. Text : The Loan to the Boathouse Steps January 2026 to July 2026. Text: 8 Edinburgh Road to Seals Craig July 2026 to August 2026

Phase 2b

Map with shading showing area of construction work on Queensferry High Street. Text : The Boathouse Steps to the Ferry Tap January 2027 to March 2027. Text: The Ferry Tap to Queensferry Museum October 2026 to January 2026.

 